01

Positive Pressure Fire Tests of Door Assemblies - US test standard

Tipo: Test standard

Standard: UL 10B, UL 10C, CAN-S/104

Clienti:

At UL's in-house laboratory in Northbrook, Chicago, Illinois, we can test closures according to the American standard. Alternatively at the UL laboratory in Rosenheim, Germany. The test is very similar to the European one, in extreme synthesis, it differs in the application at the end of the test, over 20 minutes, of the hose stream test, which is a full power hydrant jet that follows a certain pattern (a path) for a certain time. The door must not leave open spaces from which it can be glimpsed after the hose stream and the lobs must be engaged at the end of the test.
CLASSIFICATIONS
The available classifications are: 20 minutes without hose stream 20 minutes with hose stream 30 minutes with hose stream 3/4 of an hour with hose stream 1 hour with hose stream 1 and 1/2 hour with hose stream 3 hours with hose stream 4 hours with hose stream
EXPOSED SIDE
Normally, in the case of symmetrical constructions, only the side that is pulled exposed (door that opens towards the oven) is tested. If the hose stream fails in a door that has withstood fire for more than 20 minutes, the only possible classification remains 20 minutes without hose stream. It is an extremely demanding test especially for wooden doors. We have the possibility to combine, in the same test if carried out at the laboratory in Rosenheim, also the test according to the European standard EN 1634-1. With the UL 10Bstandard no positive pressure is applied (it's a bit simpler). With the UL 10Cstandard positive pressure is applied. The CAN-S/104standard is like UL 10C, but only ports that exceed the Hose Stream are classified.
TESTS FOR CONSTRUCTION COMPONENTS
Inside a door that is ULtested, accessories such as hinges, some types of gaskets and dropdown sealscan also be tested and subsequently "listed". Door closers require an additional test (endurance according to UL228), while locks are normally tested inside a metallic hollow door listed for up to 3 hours, so they are hardly suitable for testing in conjunction with the door itself.
HOW TO MAKE VARIANTS OR REPLACE COMPONENTS?
Change hinges, locks, finishes, design. Sometimes this is possible without new tests: you have to present the case to UL engineeringand a Minor Evaluationor a Major Evaluationcould be established, which complements the UL File concerning the port. The difference lies in the cost which is greater whether Minor, Major or new test.
AFTER THE TEST?
If the test is successful, which is regular to us, ULproceeds with the Follow Up Service, FUS, as you can see in the specified section of the site. clicking here.
UL DATABASE
UL listedproducts can be found and searched in the UL database, IQ Prospectorhttps://iq.ulprospector.com/ UL is not the only laboratory that can perform ULtesting, but it is the only one that can include you in the UL IQ Prospector. There are also other bodies that can carry out a test according to the UL standard, they could include you in their own database (e.g. Intertek).
INTERTEK DATABASE
Intertek's listed products can be found and searched in the construction products database https://bpdirectory.intertek.com/
UL: ONE STOP SHOP FOR THE WORLD
UL is among the laboratories included in the Middle East Civil Defencelists, with the issue of the CoC - Certificate of Conformityfor the specific country it is possible to market products in those areas. You can learn more in the section dedicated to fire resistance Middle East
UL: WE PARTICIPATE IN STANDARDISATION ACTIVITIES
Eros Chemolli is part of UL's STP10standardisation group which discusses various ULsafety standards: UL 9, fire testing of window assemblies UL 10A, coated fire doors UL 10B, fire test of doors UL 10C, positive fire pressure test of doors UL 10D, fire testing of fire protective curtains UL 14B, hardware for sliding fire doors UL 14C, hardware for swing fire doors We have recently proposed changes to UL10B/C, based on our experience.
THE CHEMOLLI FIRE CONTRIBUTION
When it comes to testing, we provide our experience and our KNOW-HOW. Having always done this type of activity, as specialists, we offer you complete advice during all the laboratory experimentation phases, from design to documentation of results. THE METHOD Listening is the most important phase of our interaction: we want you to develop a product that is the sum of your identity and your needs. First of all, we'll try to understand your real needs, the channels and the markets you want to measure yourself on. Then we will show you how the testing and certification process takes place: we need to deal with you, to fully grasp your point of view. Then, we concert a proposal that respects - compatibly with the required performances - your product lines, your production lines and, as far as possible, the potential economies of scale by using products and methodologies already consolidated in your company. EMPATHY Beyond the opportunities, which we will show you, we will then advise you what we would do, in your shoes. We advise with our experience on what, how and where to test. In which laboratory should you test? In the one that best suits your needs! THE PROJECT Once the key is turned, we prepare a project that is exhaustive of all the details. Which materials and components to use, an important part of our dialogue on which we can best advise you. In addition to this, a cost sheet and a forecast of weights, to allow you to check if your goals will be achieved. Using the best practices in the sector, we are convinced of this. ATYPICAL CONSULTANTS: WE TAKE CARE OF THE TESTING ACTIVITY A consultant gives advice, then lets the client put it into practice. We are not like this: we take off tie and put on our work clothes when needed. Once the production of the samples has been launched, we are present during the gluing of the doors, we offer support during processing and hardware installation, we proceed with our technicians to install the samples in the laboratory and we are physically present at the test. We manage the post-test documentation review phase, we illustrate the documentation and remain available for all issues related to results management.
IN DEPTH
02

Standard for Air Leakage Tests of Door Assemblies and Other Opening Protectives

Tipo: Test standard

Standard: UL 1784

Clienti:

These requirements concern the inspection of air leaks through doors and other protective elements installed in openings where the air leakage must be checked.
THE TEST
UL 1784is a test that is very similar to the European test according to EN1634-3, where the heating is similar (400degrees fahrenheit is 204 degrees), but the temperature in the test chamber must be reached, instead of 30 minutes as indicated in the European test, in 15 minutes. Smoke-proof doors normally have the addition of an "S" in the definition (e.g. FD20S). This involves an additional test in addition to the UL10b/UL10cfire test.
LISTING
UL listedproducts can be found and searched in the UL database, IQ Prospectorhttps://iq.ulprospector.com/ The category for smoke-proof doors is OPBWLeakage-rated Door Assemblies UL is not the only laboratory that can perform ULtesting, but it is the only one that can include you in the UL IQ Prospector. There are also other bodies that can carry out a test according to the UL standard, they could include you in their own database (e.g. Intertek).
AFTER THE TEST?
If the test is successful, which is regular to us, ULproceeds with the Follow Up Service, FUS, as you can see in the specified section of the site. clicking here.
THE CHEMOLLI FIRE CONTRIBUTION
When it comes to testing, we provide our experience and our KNOW-HOW. Having always done this type of activity, as specialists, we offer you complete advice during all the laboratory experimentation phases, from design to documentation of results. THE METHOD Listening is the most important phase of our interaction: we want you to develop a product that is the sum of your identity and your needs. First of all, we'll try to understand your real needs, the channels and the markets you want to measure yourself on. Then we will show you how the testing and certification process takes place: we need to deal with you, to fully grasp your point of view. Then, we concert a proposal that respects - compatibly with the required performances - your product lines, your production lines and, as far as possible, the potential economies of scale by using products and methodologies already consolidated in your company. EMPATHY Beyond the opportunities, which we will show you, we will then advise you what we would do, in your shoes. We advise with our experience on what, how and where to test. In which laboratory should you test? In the one that best suits your needs! THE PROJECT Once the key is turned, we prepare a project that is exhaustive of all the details. Which materials and components to use, an important part of our dialogue on which we can best advise you. In addition to this, a cost sheet and a forecast of weights, to allow you to check if your goals will be achieved. Using the best practices in the sector, we are convinced of this. ATYPICAL CONSULTANTS: WE TAKE CARE OF THE TESTING ACTIVITY A consultant gives advice, then lets the client put it into practice. We are not like this: we take off tie and put on our work clothes when needed. Once the production of the samples has been launched, we are present during the gluing of the doors, we offer support during processing and hardware installation, we proceed with our technicians to install the samples in the laboratory and we are physically present at the test. We manage the post-test documentation review phase, we illustrate the documentation and remain available for all issues related to results management.
IN DEPTH
03

Door Closers-Holders, With or Without Integral Smoke Detectors

Tipo: Test standard

Standard: UL 228

Clienti:

UL 228is the standard for testing door closers, whether or not they are equipped with smoke detectors. An endurance test of 100,000 cycles must be carried out. For door closers equipped with electronic components, there are many tests concerning reliability even in case of fire. UL listedproducts can be found and searched in the UL database, IQ Prospectorhttps://iq.ulprospector.com/ The category for swing door closers, Swinging Fire Door Closers, is GVEV.
IN DEPTH
04

Standard for Panic Hardware

Tipo: Test standard

Standard: UL 305

Clienti:

This standard was the result of studies, verifications, installations and manufacturing criteria used by ULhas been evaluating panic devices since 1920, when the first list of panic devices was approved for publication. UL 305was developed in particular as a test method focusing on the evaluation of panic devices for use in emergency exits. Underwriters Laboratories(UL) published the first edition of the standard in 1955 which has been in continuous use through the sixth edition today. It is also relevant to note that UL 305has become a mandatory requirement referred to in the International Building Code (IBC)published by the International Code Council (ICC). The IBC document is important for any company interested in exporting as the rules are introduced in every state of the Union through various editions. Outside the United States, content from the IBC can be found in building regulations at various locations in the Middle East. Four critical tests Durability test Emergency function test Low temperature impact test High environmental exposure test If the product is intended to be installed and used on fire door assemblies, additional tests must be performed in accordance with ANSI/UL 10C Positive Pressure Fire Tests of Door Assemblies. When a fire rating is required, the device must be tested on doors that open in and out of the furnace. For products that meet both panic and fire safety standards, the terminology changes as they are called fire exit hardware instead of panic hardware. Extract from the authorised translation of Mattew Schumann's text, UL
IN DEPTH
05

Classification for Rating Sound Insulation - Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements

Tipo: Test standard

Standard: ASTM E90-09, ASTM E413-10, ASTM E1332-16, ASTM E 2235-04

Clienti:

Acoustic door tests according to American STC: Reverberation chamber test method for determining sound insulation.
STANDARDS USED
The standards used to determine the STC value are: ASTM E90-09 "Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements" ASTM E413-10 "Classification for Rating Sound Insulation" ASTM E1332-16 "Standard Classification for Rating Outdoor-Indoor Sound Attenuation" ASTM E 2235-04 "Standard Test Method for Determination of Decay Rates for Use in Sound Insulation Test Methods"
THE CALCULATION
The calculation of the STC (Sound Transmission Class)index, according to the E413standard, is based on the values calculated for each one-third octave frequency band from 125 Hz to 4000 Hz. The experimental curve is evaluated and compared with the reference curve. Then the curve comparison method is applied up to the point where the sum of the unfavourable differences between the relative curve values are on the reference curve less than or equal to 32 dB and the maximum deficiency at any one frequency does not exceed 8 dB. The single number rating is given by the value of the reference contour shifted to 500 Hz.
TL ED OITC
The classification, according to the E1332standard, requires the measurement of transmission loss (TL - Transmission Loss) in the third octave band from 80 to 4000 Hzfor the determination of the OITC (Outdoor-Indoor Transmission Class) index. The same header port for Rw and STC could give similar results, although sometimes American results are slightly more "optimistic" than European ones. By changing the band and method, the results may vary.
THE CHEMOLLI FIRE CONTRIBUTION
When it comes to testing, we provide our experience and our KNOW-HOW. Having always done this type of activity, as specialists, we offer you complete advice during all the laboratory experimentation phases, from design to documentation of results. THE METHOD Listening is the most important phase of our interaction: we want you to develop a product that is the sum of your identity and your needs. First of all, we'll try to understand your real needs, the channels and the markets you want to measure yourself on. Then we will show you how the testing and certification process takes place: we need to deal with you, to fully grasp your point of view. Then, we concert a proposal that respects - compatibly with the required performances - your product lines, your production lines and, as far as possible, the potential economies of scale by using products and methodologies already consolidated in your company. EMPATHY Beyond the opportunities, which we will show you, we will then advise you what we would do, in your shoes. We advise with our experience on what, how and where to test. In which laboratory should you test? In the one that best suits your needs! THE PROJECT Once the key is turned, we prepare a project that is exhaustive of all the details. Which materials and components to use, an important part of our dialogue on which we can best advise you. In addition to this, a cost sheet and a forecast of weights, to allow you to check if your goals will be achieved. Using the best practices in the sector, we are convinced of this. ATYPICAL CONSULTANTS: WE TAKE CARE OF THE TESTING ACTIVITY A consultant gives advice, then lets the client put it into practice. We are not like this: we take off tie and put on our work clothes when needed. Once the production of the samples has been launched, we are present during the gluing of the doors, we offer support during processing and hardware installation, we proceed with our technicians to install the samples in the laboratory and we are physically present at the test. We manage the post-test documentation review phase, we illustrate the documentation and remain available for all issues related to results management.
01

Positive Pressure Fire Tests of Door Assemblies - US test standard

Tipo: Test standard

Standard: UL 10B, UL 10C, CAN-S/104

Clienti:

At UL's in-house laboratory in Northbrook, Chicago, Illinois, we can test closures according to the American standard. Alternatively at the UL laboratory in Rosenheim, Germany. The test is very similar to the European one, in extreme synthesis, it differs in the application at the end of the test, over 20 minutes, of the hose stream test, which is a full power hydrant jet that follows a certain pattern (a path) for a certain time. The door must not leave open spaces from which it can be glimpsed after the hose stream and the lobs must be engaged at the end of the test.
CLASSIFICATIONS
The available classifications are: 20 minutes without hose stream 20 minutes with hose stream 30 minutes with hose stream 3/4 of an hour with hose stream 1 hour with hose stream 1 and 1/2 hour with hose stream 3 hours with hose stream 4 hours with hose stream
EXPOSED SIDE
Normally, in the case of symmetrical constructions, only the side that is pulled exposed (door that opens towards the oven) is tested. If the hose stream fails in a door that has withstood fire for more than 20 minutes, the only possible classification remains 20 minutes without hose stream. It is an extremely demanding test especially for wooden doors. We have the possibility to combine, in the same test if carried out at the laboratory in Rosenheim, also the test according to the European standard EN 1634-1. With the UL 10Bstandard no positive pressure is applied (it's a bit simpler). With the UL 10Cstandard positive pressure is applied. The CAN-S/104standard is like UL 10C, but only ports that exceed the Hose Stream are classified.
TESTS FOR CONSTRUCTION COMPONENTS
Inside a door that is ULtested, accessories such as hinges, some types of gaskets and dropdown sealscan also be tested and subsequently "listed". Door closers require an additional test (endurance according to UL228), while locks are normally tested inside a metallic hollow door listed for up to 3 hours, so they are hardly suitable for testing in conjunction with the door itself.
HOW TO MAKE VARIANTS OR REPLACE COMPONENTS?
Change hinges, locks, finishes, design. Sometimes this is possible without new tests: you have to present the case to UL engineeringand a Minor Evaluationor a Major Evaluationcould be established, which complements the UL File concerning the port. The difference lies in the cost which is greater whether Minor, Major or new test.
AFTER THE TEST?
If the test is successful, which is regular to us, ULproceeds with the Follow Up Service, FUS, as you can see in the specified section of the site. clicking here.
UL DATABASE
UL listedproducts can be found and searched in the UL database, IQ Prospectorhttps://iq.ulprospector.com/ UL is not the only laboratory that can perform ULtesting, but it is the only one that can include you in the UL IQ Prospector. There are also other bodies that can carry out a test according to the UL standard, they could include you in their own database (e.g. Intertek).
INTERTEK DATABASE
Intertek's listed products can be found and searched in the construction products database https://bpdirectory.intertek.com/
UL: ONE STOP SHOP FOR THE WORLD
UL is among the laboratories included in the Middle East Civil Defencelists, with the issue of the CoC - Certificate of Conformityfor the specific country it is possible to market products in those areas. You can learn more in the section dedicated to fire resistance Middle East
UL: WE PARTICIPATE IN STANDARDISATION ACTIVITIES
Eros Chemolli is part of UL's STP10standardisation group which discusses various ULsafety standards: UL 9, fire testing of window assemblies UL 10A, coated fire doors UL 10B, fire test of doors UL 10C, positive fire pressure test of doors UL 10D, fire testing of fire protective curtains UL 14B, hardware for sliding fire doors UL 14C, hardware for swing fire doors We have recently proposed changes to UL10B/C, based on our experience.
THE CHEMOLLI FIRE CONTRIBUTION
When it comes to testing, we provide our experience and our KNOW-HOW. Having always done this type of activity, as specialists, we offer you complete advice during all the laboratory experimentation phases, from design to documentation of results. THE METHOD Listening is the most important phase of our interaction: we want you to develop a product that is the sum of your identity and your needs. First of all, we'll try to understand your real needs, the channels and the markets you want to measure yourself on. Then we will show you how the testing and certification process takes place: we need to deal with you, to fully grasp your point of view. Then, we concert a proposal that respects - compatibly with the required performances - your product lines, your production lines and, as far as possible, the potential economies of scale by using products and methodologies already consolidated in your company. EMPATHY Beyond the opportunities, which we will show you, we will then advise you what we would do, in your shoes. We advise with our experience on what, how and where to test. In which laboratory should you test? In the one that best suits your needs! THE PROJECT Once the key is turned, we prepare a project that is exhaustive of all the details. Which materials and components to use, an important part of our dialogue on which we can best advise you. In addition to this, a cost sheet and a forecast of weights, to allow you to check if your goals will be achieved. Using the best practices in the sector, we are convinced of this. ATYPICAL CONSULTANTS: WE TAKE CARE OF THE TESTING ACTIVITY A consultant gives advice, then lets the client put it into practice. We are not like this: we take off tie and put on our work clothes when needed. Once the production of the samples has been launched, we are present during the gluing of the doors, we offer support during processing and hardware installation, we proceed with our technicians to install the samples in the laboratory and we are physically present at the test. We manage the post-test documentation review phase, we illustrate the documentation and remain available for all issues related to results management.
IN DEPTH
02

Standard for Air Leakage Tests of Door Assemblies and Other Opening Protectives

Tipo: Test standard

Standard: UL 1784

Clienti:

These requirements concern the inspection of air leaks through doors and other protective elements installed in openings where the air leakage must be checked.
THE TEST
UL 1784is a test that is very similar to the European test according to EN1634-3, where the heating is similar (400degrees fahrenheit is 204 degrees), but the temperature in the test chamber must be reached, instead of 30 minutes as indicated in the European test, in 15 minutes. Smoke-proof doors normally have the addition of an "S" in the definition (e.g. FD20S). This involves an additional test in addition to the UL10b/UL10cfire test.
LISTING
UL listedproducts can be found and searched in the UL database, IQ Prospectorhttps://iq.ulprospector.com/ The category for smoke-proof doors is OPBWLeakage-rated Door Assemblies UL is not the only laboratory that can perform ULtesting, but it is the only one that can include you in the UL IQ Prospector. There are also other bodies that can carry out a test according to the UL standard, they could include you in their own database (e.g. Intertek).
AFTER THE TEST?
If the test is successful, which is regular to us, ULproceeds with the Follow Up Service, FUS, as you can see in the specified section of the site. clicking here.
THE CHEMOLLI FIRE CONTRIBUTION
When it comes to testing, we provide our experience and our KNOW-HOW. Having always done this type of activity, as specialists, we offer you complete advice during all the laboratory experimentation phases, from design to documentation of results. THE METHOD Listening is the most important phase of our interaction: we want you to develop a product that is the sum of your identity and your needs. First of all, we'll try to understand your real needs, the channels and the markets you want to measure yourself on. Then we will show you how the testing and certification process takes place: we need to deal with you, to fully grasp your point of view. Then, we concert a proposal that respects - compatibly with the required performances - your product lines, your production lines and, as far as possible, the potential economies of scale by using products and methodologies already consolidated in your company. EMPATHY Beyond the opportunities, which we will show you, we will then advise you what we would do, in your shoes. We advise with our experience on what, how and where to test. In which laboratory should you test? In the one that best suits your needs! THE PROJECT Once the key is turned, we prepare a project that is exhaustive of all the details. Which materials and components to use, an important part of our dialogue on which we can best advise you. In addition to this, a cost sheet and a forecast of weights, to allow you to check if your goals will be achieved. Using the best practices in the sector, we are convinced of this. ATYPICAL CONSULTANTS: WE TAKE CARE OF THE TESTING ACTIVITY A consultant gives advice, then lets the client put it into practice. We are not like this: we take off tie and put on our work clothes when needed. Once the production of the samples has been launched, we are present during the gluing of the doors, we offer support during processing and hardware installation, we proceed with our technicians to install the samples in the laboratory and we are physically present at the test. We manage the post-test documentation review phase, we illustrate the documentation and remain available for all issues related to results management.
IN DEPTH
03

Door Closers-Holders, With or Without Integral Smoke Detectors

Tipo: Test standard

Standard: UL 228

Clienti:

UL 228is the standard for testing door closers, whether or not they are equipped with smoke detectors. An endurance test of 100,000 cycles must be carried out. For door closers equipped with electronic components, there are many tests concerning reliability even in case of fire. UL listedproducts can be found and searched in the UL database, IQ Prospectorhttps://iq.ulprospector.com/ The category for swing door closers, Swinging Fire Door Closers, is GVEV.
IN DEPTH
04

Standard for Panic Hardware

Tipo: Test standard

Standard: UL 305

Clienti:

This standard was the result of studies, verifications, installations and manufacturing criteria used by ULhas been evaluating panic devices since 1920, when the first list of panic devices was approved for publication. UL 305was developed in particular as a test method focusing on the evaluation of panic devices for use in emergency exits. Underwriters Laboratories(UL) published the first edition of the standard in 1955 which has been in continuous use through the sixth edition today. It is also relevant to note that UL 305has become a mandatory requirement referred to in the International Building Code (IBC)published by the International Code Council (ICC). The IBC document is important for any company interested in exporting as the rules are introduced in every state of the Union through various editions. Outside the United States, content from the IBC can be found in building regulations at various locations in the Middle East. Four critical tests Durability test Emergency function test Low temperature impact test High environmental exposure test If the product is intended to be installed and used on fire door assemblies, additional tests must be performed in accordance with ANSI/UL 10C Positive Pressure Fire Tests of Door Assemblies. When a fire rating is required, the device must be tested on doors that open in and out of the furnace. For products that meet both panic and fire safety standards, the terminology changes as they are called fire exit hardware instead of panic hardware. Extract from the authorised translation of Mattew Schumann's text, UL
IN DEPTH
05

Classification for Rating Sound Insulation - Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements

Tipo: Test standard

Standard: ASTM E90-09, ASTM E413-10, ASTM E1332-16, ASTM E 2235-04

Clienti:

Acoustic door tests according to American STC: Reverberation chamber test method for determining sound insulation.
STANDARDS USED
The standards used to determine the STC value are: ASTM E90-09 "Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements" ASTM E413-10 "Classification for Rating Sound Insulation" ASTM E1332-16 "Standard Classification for Rating Outdoor-Indoor Sound Attenuation" ASTM E 2235-04 "Standard Test Method for Determination of Decay Rates for Use in Sound Insulation Test Methods"
THE CALCULATION
The calculation of the STC (Sound Transmission Class)index, according to the E413standard, is based on the values calculated for each one-third octave frequency band from 125 Hz to 4000 Hz. The experimental curve is evaluated and compared with the reference curve. Then the curve comparison method is applied up to the point where the sum of the unfavourable differences between the relative curve values are on the reference curve less than or equal to 32 dB and the maximum deficiency at any one frequency does not exceed 8 dB. The single number rating is given by the value of the reference contour shifted to 500 Hz.
TL ED OITC
The classification, according to the E1332standard, requires the measurement of transmission loss (TL - Transmission Loss) in the third octave band from 80 to 4000 Hzfor the determination of the OITC (Outdoor-Indoor Transmission Class) index. The same header port for Rw and STC could give similar results, although sometimes American results are slightly more "optimistic" than European ones. By changing the band and method, the results may vary.
THE CHEMOLLI FIRE CONTRIBUTION
When it comes to testing, we provide our experience and our KNOW-HOW. Having always done this type of activity, as specialists, we offer you complete advice during all the laboratory experimentation phases, from design to documentation of results. THE METHOD Listening is the most important phase of our interaction: we want you to develop a product that is the sum of your identity and your needs. First of all, we'll try to understand your real needs, the channels and the markets you want to measure yourself on. Then we will show you how the testing and certification process takes place: we need to deal with you, to fully grasp your point of view. Then, we concert a proposal that respects - compatibly with the required performances - your product lines, your production lines and, as far as possible, the potential economies of scale by using products and methodologies already consolidated in your company. EMPATHY Beyond the opportunities, which we will show you, we will then advise you what we would do, in your shoes. We advise with our experience on what, how and where to test. In which laboratory should you test? In the one that best suits your needs! THE PROJECT Once the key is turned, we prepare a project that is exhaustive of all the details. Which materials and components to use, an important part of our dialogue on which we can best advise you. In addition to this, a cost sheet and a forecast of weights, to allow you to check if your goals will be achieved. Using the best practices in the sector, we are convinced of this. ATYPICAL CONSULTANTS: WE TAKE CARE OF THE TESTING ACTIVITY A consultant gives advice, then lets the client put it into practice. We are not like this: we take off tie and put on our work clothes when needed. Once the production of the samples has been launched, we are present during the gluing of the doors, we offer support during processing and hardware installation, we proceed with our technicians to install the samples in the laboratory and we are physically present at the test. We manage the post-test documentation review phase, we illustrate the documentation and remain available for all issues related to results management.

Ask for information about testing